Seabank Power Limited, a 50:50 joint venture between
BG Energy Holdings Limited, a subsidiary of BG Group
plc, and Scottish and Southern Energy plc, announced
today that the 1,140 megawatts combined-cycle gas turbine
(CCGT) power station at Hallen, near Bristol, has entered
full commercial operation.
Construction of the £435 million development began in
January 1996 and was carried out in two phases. The first,
which included remediation of a brown field site, was formally
handed over to Seabank Power in March 2000. It has the capacity
to generate 755 MW of electricity. Phase II development, with
a capacity of 385 MW, was started in January 1999 and has been
delivered on budget and to schedule.
Jon Wormley, Executive Vice President, BG Group plc,
said: "Through this investment BG Group has been
able to develop jointly a first rate power station and
forge a strong partnership with our co-venturers. Seabank
demonstrates our capability to create strategic linkages
between our upstream interests and downstream investments."
Dr James Martin, Generation Director of Scottish and
Southern Energy plc, said: "The addition of the
output of Seabank, operating to efficiencies over 57
per cent, to our portfolio reinforces Scottish and Southern
Energy as the youngest, most flexible, most efficient
and environmental of the major generators. Following
the re-powering of our Peterhead Power Station on time
and on budget, the delivery of Phase II at Seabank in
similar vein is no mean achievement and a credit to the
teams involved."
Nigel Shaw, Chairman, Seabank Power Limited, said: "Seabank
Power has realised a huge milestone with delivery of
this project. We have seen Phase I come to fruition and
operate efficiently whilst the speed of Phase II construction,
taking two years, has been remarkable. The power station
is now one of the UK's most efficient and an environmental
leader in its class."
The station was built by Siemens plc on 40 acres of
a former gasworks site. An additional surrounding area
of 40 acres has also been landscaped. Three Siemens V94.3A
gas turbines utilise state-of-the-art technology and
operate with high efficiencies (over 57 per cent) compared
to 35 per cent for conventional power stations.
Natural gas to the power plant, provided by Scottish
and Southern Energy (SSE), is sourced via a specially
constructed 26 kilometres 42-inch underground pipeline
which links to the national gas network at Pucklechurch,
Bristol. A gas compressor station, using two 2.5 MVA
electrically driven compressors, is located at this site
and is capable of packing gas to pressures in excess
of 70 bar. BG Group, via a subsidiary company, BG International
Limited, is supplying gas to SSE under an eight-year
gas sales agreement.
Total electricity output from the power plant is contracted
under separate arrangements to SSE and sold into the
marketplace. The site is connected to the national electricity
grid via a 400,000 volt (400kV) substation. The plant's
total generating capacity is sufficient to supply the
City of Bristol and surrounding areas.
At peak construction times, the project development
employed in excess of 1,000 employees. The station currently
employs 55 staff.
Notes to Editors
BG Group plc wholly owns and operates the 1,057 MW Ballylumford
Power Station in Northern Ireland, which generates over
half of the Province's electricity needs. It has a 40
per cent interest in the Santa Rita 1,000 MW power plant
in the Philippines and is currently developing an adjacent
500 MW plant. In addition, it has a 20 per cent shareholding
in Genting Sanyen Power, one of Malaysia's main power
stations, and has power generation interests in Italy.
Scottish and Southern Energy plc will have over 7,000
MW by 2002 from its own generation or on long-term contract.
It is the largest generator of renewable energy in the
UK. The company is the largest network asset operator
in the UK and has four million electricity and one million
gas customers.
|